Barry Schools

Additions and Renovations For: Barry Community Unit School District No. 1 Barry, Pike Co, IL.

Barry Elementary programs include An all-day kindergarten, an “at risk” preschool and special education programs. Within this Addition specialists provide instruction in music, physical education, art, reading and math in the new facility. The construction was completed without loss of teaching space. The existing buildings, and the sloping site area presented challenges that were overcome by developing a comprehensive phased construction plan that addressed complete accessibility throughout the complex.

Project Information:

Cost: $3,813,669
Grades Housed K-12
Capacity: 600
Occupancy: September, 2000
Square footage: 53,150 S.F.
New: 31,000 S.F.
Renovated: 22,150 S.F.
Cost /S.F.: $71.75
Client Contact:
Dr Shari L. Marshall

Project Team:

Anthony Crane, AIA
Architect
Darin Prost, AIA Architect
Tanya Hilliard Intern Architect
Todd Moore, PE. Mechanical
Joel Peck Electrical
Dale Wuestenfeld Structural
Richard Walz
Plumbing